1. Is the approval for ready mix supplier received
2. Whether time of transport after batching at plant & type of retarder added are noted
3. Whether temperature of concrete and atmospheric temperature at site checked to be within specified limits
4. Are the slump cone, cube moulds & curing tank available
5. Are the concrete vibrators available and have been checked in advance whether they are in working condition
6. Whether approval for concrete pour inspection request from R.E received
2. Whether time of transport after batching at plant & type of retarder added are noted
3. Whether temperature of concrete and atmospheric temperature at site checked to be within specified limits
4. Are the slump cone, cube moulds & curing tank available
5. Are the concrete vibrators available and have been checked in advance whether they are in working condition
6. Whether approval for concrete pour inspection request from R.E received
7. Is the sequence of concreting agreed with R.E.
8. Reinforcement, form work are checked as per the checklist
9. Whether cover blocks checked and found as per requirement
10. Whether slump test carried out and is within the permissible limit
11. Whether the cubes are casted from different truck mixers
12. Whether compaction of concrete carried out while doing the concreting
13. Whether surface cracks checked after 1-2 hours and wet hessien cloth laid
14. Whether post concrete inspection done and repair works to honeycombing, if found done in a proper way
15. Whether curing is done for the number of days as specified
16. Has the co-ordination with M&E services done as per the checklist.
8. Reinforcement, form work are checked as per the checklist
9. Whether cover blocks checked and found as per requirement
10. Whether slump test carried out and is within the permissible limit
11. Whether the cubes are casted from different truck mixers
12. Whether compaction of concrete carried out while doing the concreting
13. Whether surface cracks checked after 1-2 hours and wet hessien cloth laid
14. Whether post concrete inspection done and repair works to honeycombing, if found done in a proper way
15. Whether curing is done for the number of days as specified
16. Has the co-ordination with M&E services done as per the checklist.